British Columbia · Electrical engineering · Energy storage
A facility owner retained us to size a behind-the-meter battery energy storage system and prepare the engineering for a utility incentive application.
Challenge
The incentive is capped by nominated energy, by nominated power and by a share of eligible cost, and the nominated capacity is limited by the facility's average demand during peak periods. A system sized without that calculation either leaves incentive unclaimed or carries capacity the programme will not pay for. The owner also wanted reserve capacity held back for the facility's own critical loads.
Approach
- Calculated average peak-period demand from the facility's interval data
- Sized the battery and inverters, and split the capacity between the amount nominated to the utility and the owner's reserve
- Designed the interconnection: transformation to the facility's distribution voltage, metering for two-way flow, and isolation from the grid on loss of utility supply
- Specified the connection to the utility's distributed energy resource management system, with the control points list
- Prepared the single-line diagram, eligible cost budget and incentive calculation
Outcome
The application identified which of the three caps governed and the incentive that followed from it, and set out the long-term dispatch and availability terms the owner was accepting.
Services applied
Electrical engineering · Utility interconnection studies · Electrical service connections