Most buildings we are asked to remediate are operating. That constraint shapes everything: the sequencing, the temporary systems, and often the design itself.
Remediation work also arrives with history. Something was built to a code that has since changed, or installed in a way that has not held up, or modified over years by people who did not document what they did. Establishing what is actually there is the first engineering task, not a preliminary to it.
What we do
Condition assessment. Establishing the real state and remaining capacity of existing electrical and mechanical systems, including where record drawings no longer match the building.
Code compliance upgrades. Bringing existing installations to current code, and identifying where legacy conditions are permitted to remain and where they are not.
Capacity verification and upgrade design. Whether the existing service can carry a new load, and what has to change if it cannot.
Failure remediation. Correcting the conditions that caused a failure — frequently following a forensic investigation that established root cause.
Phased work on operating facilities. Sequencing, tie-in planning and temporary systems for buildings that cannot close.
The design constraint people underestimate
On an operating building, the tie-in window is often the binding constraint on the design — not the technical requirement. A scheme that is elegant but needs a twelve-hour outage may be unbuildable where a less elegant one that tolerates a two-hour window is not.
We ask what outage the facility can actually take before we design, rather than presenting a design and discovering the answer afterwards.